Take a look at some of our successful projects

Leeds City Centre York Rd Fly-Over – Bridge Strengthening Works

The existing fly-over parapets required strengthening. They were demolished using hydro-demolition techniques and re-cast as per the existing profile. Ancillary civils works were then carried out during the parapet programme.

Scope of Works

  • Removal of the existing parapet steel railings.
  • Drilling dowels and fixing re-inforcement for the new parapet bays.
  • To erect parapet shutters and new parapet bays.
  • Removal and replacement of all kerbs across the fly-over.
  • New drainage to the fly-over deck and refurbishment of the existing gullies.
  • Removal and subsequent re-surfacing of the footpaths and associated slip-road verges.
  • Removal of all hydro-demolition debris from scaffolding off site to licensed facilities.
  • Indepth supplied all management, labour, plant and materials for the project.

Cookies

This website uses cookies. You can read more information about why we do this, and what they are used for here.

Accept Decline